Archive. Year 2017. January-June.

Archive. Year 2016. July-December.

Archive. Year 2016. January-June.

Archive. Year 2015. July-December.

Archive. Year 2015. January-June.

Archive. Year 2014. July-December.

Archive. Year 2014. January-June.

Archive. Year 2013. July-December.

Archive. Year 2013. January-June.

Archive. Year 2012. July-December.

Archive. Year 2012. January-June.

Archive. Year 2011.

Archive. Year 2010.

Archive. Year 2009.

 

 

 

Archive

November 15, 2017

SS Tobolsk has started hydraulic strength testing by 3.8 MPa pressure and pressure density of 1 MPa of process pipelines at the project «Construction of polypropylene production plant of 500 thousand tons annual capacity». The Subcontractors SU-6 Neftegazmontazh, JSC and Kazmekhanomontazh, LLP, tested the first five line circuits in the amount of 21 lines. All in all it is planned to test 775 lines by the end of the year.


November 14, 2017

The Direction on construction of «Polypropylene production plant of 500 thousand tons annual capacity» for the project «West-Siberian complex of raw hydrocarbons deep conversion into polyolefins which capacity is 2.0 million tons per year, including corresponding off-site facilities» performed the following works:

  • foundation in the amount of 7,280 m3 (99%)
  • cast-in-situ concrete placement in the amount of 11,421 m3 (99%)
  • installation of reinforced concrete structures in the amount of 1,064 m3 (95%)
  • brick laying in the amount of 999 m3 (95%)
  • installation of underground pipelines in the amount of 5,223 m (95%)
  • well development in the amount of 278 pcs. (87%)
  • backfilling in the amount of 126,283 m3 (82,5%)
  • painting of pipelines in the amount of 9,052 m2 (44%)
  • structural steel erection in the amount of 7,445 tn (92%)
  • installation of heating, ventilation and air conditioning in the amount of 3,659 m2 (38%)
  • installation of equipment in the amount of 2,017 tn (57%)
  • installation of process pipelines in the amount of 159,541 m (71%).


November 13, 2017

Within the frames of implementation of the project «West-Siberian complex of raw hydrocarbons deep conversion into polyolefins which capacity is 2.0 million tons per year, including corresponding off-site facilities» and to perform contractual obligations the off-site facilities construction project office of the SS Tobolsk performed the following works:

  • structural steel erection of the frame of the facility «Boiler room» in the volume of 512 tn (58 %)
  • fireproofing of metal structures in the volume of 2,560 m2 (59 %)
  • erection of the divide wall and pedestal by brick laying in the volume of 196 m3 (61 %).

October 31, 2017

Promstroi, JSC accepted a group of future specialists in the industrial construction. More…


October 31, 2017

Promstroi, JSC took part in the competition «The best Contractor in the field of HSE» at the project of «Combined Oil Refining Unit Euro+». The management of the Client took a favourable view of the work of the Company noting a prompt provision of documentation, a high-quality performance of works, a high level of the safety culture. Promstroi, JSC took the second place among the contractors working at the project.


October 25, 2017

Installation of the first level of the radiation chamber of the reforming furnace H201/202/203/204 of 180 tons average weight was completed at the process plant «Catalytic reformer with gasoline fraction hydro treating unit» at the project «Combined Oil Refining Unit (CORU) Euro+».


October 05, 2017

Works on installation of the roof profile sheeting are being performed at a fast pace at the project «Logistics platform» within the frames of implementation of the project «West-Siberian complex of raw hydrocarbons deep conversion into polyolefins which capacity is 2.0 million tons per year, including corresponding off-site facilities». The daily pace of installation is 2.5 thousand m2.


October 04, 2017

On September 23 the Construction Direction of Promstroi, JSC performed installation of the unique unit of heavy equipment, the key installation unit, where polypropylene is generated, the loop polymerization reactor with the involvement of machinery and specialists of SOPiG, LLC at title 51200/03 «Polymerization reactor» at the construction facility «Polypropylene Production Plant of 500 thousand tons annual capacity». The Liebherr cranes of 750 and 260 tons capacity were engaged in installation of the reactor weighing 230 tons and 60 meters height at the design mark of +9620.


October 03, 2017

On October 03 the Structural Subdivision «Moscow Oil Refinery construction division» performed pre-assembly of the first circle of the radiation chamber of the reformer H201/202/203/204 followed by installation in the design position at the processing unit «Catalytic reformer with gasoline fraction hydro treating unit» at the project «Combined oil refining unit EURO +».


September 26, 2017

On September 23 the Direction on construction of off-site facilities carried out installation of 5 units of water boilers and 2 units of steam boilers at the facility «Boiler room». The caterpillar cranes Liebherr of 500 tons lifting capacity was involved in installation of the large-sized equipment of 256 tons total weight. All works were carried out in accordance with the developed project for implementation of construction operations in compliance with HSE requirements.


September 18, 2017

The Construction Direction of Promstroi, JSC performed installation of the unique unit of heavy equipment - the capacity of the heavy pressure discharge system at title 51200/09 «Discharge system» at the construction facility «Polypropylene Production Plant of 500 thousand tons annual capacity». The Liebherr cranes of 750 and 350 tons capacity were engaged in installation by a single lift of the most heavy unit of the equipment weighing 170 tons and 19.5 meters height at the design mark of +6,400. All works were carried out in accordance with the developed project for implementation of construction operations in compliance with HSE requirements.


September 12, 2017

The off-site facilities construction project office of Tobolskiy branch performed erection of 99.87 tons of metal structures (63%) within the frames of implementation of the project «West-Siberian complex of raw hydrocarbons deep conversion into polyolefins which capacity is 2.0 million tons per year, including corresponding off-site facilities» and to perform contractual obligations at the facility «Boiler plant». Now there are works in progress on metal structures erection for chimneys with a height of 60 m.


September 08, 2017

Works on pre-assembly and erection of metal structures are being performed at a fast pace at the project «Logistics platform» in framework of implementation of the project «West-Siberian complex of raw hydrocarbons deep conversion into polyolefins which capacity is 2.0 million tons per year, including corresponding off-site facilities»». The daily pace of metal structures erection is 75 tons.


September 07, 2017

PROMSTROI GROUP, JSC, Yamata and ZapSibNeftekhim, LLC signed the tripartite agreement for performance of the whole complex of works at the facility «Logistics platform» in framework of implementation of the project «West-Siberian complex of raw hydrocarbons deep conversion into polyolefins which capacity is 2.0 million tons per year, including corresponding off-site facilities»», where PROMSTROI GROUP, JSC is the General Contractor. Period of work performance is from August 2017 to October 2018.


September 07, 2017

Kazmekhanomontazh, LLP directed by the Moscow Refinery Project Office of Promstroi, JSC at the project «Combined Oil Refining Unit Euro+» successfully completed installation of the first set of in-vessel internals of the diolefin reactor R-250 of the unit «Catalytic reformer with gasoline fraction hydro treating unit»

  • arrangement of 9,790 m3 of reinforced concrete structures – 76%
  • production of 66,505 inches of pipeline assemblies – 33%
  • installation of 227 tons of technological pipelines – 10%
  • erection of 4,050 tons of metal structures – 47%
  • installation of 83 units of technological equipment – 38%

September 05, 2017

SU-6 Neftegazmontazh, JSC started installation of process pipelines at «Polypropylene production plant of 500 thousand tons annual capacity» and «Interfactory pipe-rack for process pipelines» at the project «West-Siberian complex of raw hydrocarbons deep conversion into polyolefins which capacity is 2.0 million tons per year, including corresponding off-site facilities». Works are being performed by skilled professionals of the welding industry. A step-by-step testing of welding joints is carried out by specialists of the Quality Assurance Service at each stage of production of work. In accordance with the Contract the Company will perform welding of 22,296m of the process pipelines having diameters from 57 mm to 720 mm.


August 30, 2017

Kazmekhanomontazh, LPP and Saratov Oil Refinery, JSC concluded a contract for overhaul works at the block of the columns at CDU-VDU-6 of the production No.1 during the shutdown maintenance at Saratov Oil Refinery, JSC. The period of work performance is from September to October 2017. The mobilization of human and technical resources has started.


August 30, 2017

On August 14 Uralmontazhavtomatika, JSC started laying the electrical cable and the trunk cable of instrumentation and controls at the project of «Construction of Polypropylen Production unit of 500 thousand tons annual capacity». As of August 29, 2017 70 km of cable products were laid.


August 29, 2017

Promstroi, JSC and ZapSibNeftekhim, LLC signed KS-11 forms which confirm acceptance of the first, the second and the third group of facilities at the project of «Construction of temporary rotational camp and field offices» where the Company was the General Contractor.


August 28, 2017

Inzhpromstroi, LLC obtained a license BLG 80779 TE for the right of exploration and production of sand within the limits of Bardagonskoye-1 field, including mining operations waste management and processing plants connected with it in a volume of 5,372.6 thousand m3. The period of validity of the licence is from 18.08.2017 to 31.12.2032.


August 17, 2017

Under performance of a contractual obligation by Tobolskiy Branch of Promstroi JSC at the current moment on the project «Construction of Polypropylene production plant of 500 thousand tons annual capacity» the following scope of work have been performed:

  • concrete works (including prefabricated reinforced concrete) (18 758 m3) - 93%
  • installation of underground pipelines (4 930 meters) - 90%
  • wells development (264 pcs.) - 83.5%
  • prefabrication and installation of above-ground pipelines (128 434 dd) - 58%
  • installation of metal structures (5 125 tons) - 63.5%
  • backfilling (159 053 m3) -85.5%
  • painting (6,993 m2) - 26.15%
  • interior furnishing (8 893 m2) - 27%.

August 11, 2017

The tower crane POTAIN MC310K12 having 12 tons lifting capacity began operations at the construction facility «Combined Oil Refining Unit Euro+» of Gazpromneft-MNPZ, JSC. Involvement of the tower crane will compensate the negative factors of the lack of space at site and it will increase a progress speed of installation works at the 3rd and 4th tiers of the central pipe-rack. The lifting equipment is involved in performance of work on industrial pipelining, installation of the process equipment and erection of metal structures.


August 07, 2017

Tobolskiy branch of Promstroi, JSC successfully performed the first hydroproof testing of the pressure pipeline of K4Vn network of 1.5 Mpa pressure (240 m), the free-flow pipeline of 1, 4 network (124 m) and 7 units of wells at the project of Construction of Polypropylene production plant of 500 thousand tons annual capacity.


 

Promstroi Group
of Companies


 

PROMSTROI-GROUP
JSC

Moscow

 
 

Subsidiaries

 

Promstroi
JSC

Nyagan (KMAD)

 

Spetsializirovannoye
Upravlenie No.6
JSC

Stavropol

 

Uralmontazhavtomatika
OJSC

Tyumen

 

KAZMEKHANOMONTAZH
LLP

Republic of Kazakhstan,
Almaty

 

Novopolotsk Metal
Structures Plant
JV LLC

Republic of Belarus,
Novopolotsk

 

Inzhpromstroi
LLC

Blagoveshchensk

 

Associated
undertakings

Talspetsstroi
LLC

Nyagan (KMAD)