Рус

Archive. Year 2018. January-June.

Archive. Year 2017. July-December.

Archive. Year 2017. January-June.

Archive. Year 2016. July-December.

Archive. Year 2016. January-June.

Archive. Year 2015. July-December.

Archive. Year 2015. January-June.

Archive. Year 2014. July-December.

Archive. Year 2014. January-June.

Archive. Year 2013. July-December.

Archive. Year 2013. January-June.

Archive. Year 2012. July-December.

Archive. Year 2012. January-June.

Archive. Year 2011.

Archive. Year 2010.

Archive. Year 2009.

 

 

 

Archive

September 22, 2018

Promstroi, JSC involved in the construction of the object «Increase in the production capacity of thermoplastic elastomers from 50 to 100 thousand tons per year».

Promstroi, JSC and Voronezhsintezkauchuk, JSC signed a General contract for the implementation of a complex of construction and installation works in the framework of the project SIBUR holding «Increase in the production capacity of thermoplastic elastomers from 50 to 100 thousand tons per year at Voronezhsintezkauchuk, JSC».
The contract provides for civil works, supply and installation of steel structures, installation of process pipelines and equipment, corrosion protection, fire protection, insulation, electrical work and instrumentation.
Completion of works in the area of responsibility of Promstroi, JSC is planned in January 2020.


September 20, 2018

The project office of OP Omsk took part in the review competition at the Omsk OCP construction project for the Omsk Refinery. The organizer was NIPIGAZ, JSC. Promstroi, JSC was awarded with letters of thanks in the nominations:

  • prevention of the accident / timely response
  • for active participation in ensuring work safety at the construction site of the work process

Congratulations to colleagues!


September 20, 2018

LLC «NZTM» became the winner of the XV Anniversary Republican professional competition «The Best construction product of the year - 2018».
Our enterprise - SOOO «Novopolotsk plant of technological metal structures» in the Republic of Belarus won in the nomination: «The Best complex system, technical solution in construction». Colleagues provided for the main professional competition of the Republic in the field of construction of metal structures for reinforcement of skip and cage shafts of Ust-yayvinsky mine. The jury of the competition noted the high technical solutions, performance, consumer properties of the product submitted to the competition and a decent level of production.
The organizers of the XV Anniversary Republican professional competition «The Best construction product of the year-2018» were:

  • Belarusian national technical Institute
  • RUE «Institute BelNIIS»
  • BSC «Business media»

We congratulate our colleagues on receiving such a significant award!


September 10, 2018

The progress of the construction of the Logistic Platform facility within the framework of the West Siberian complex of deep processing of hydrocarbon raw materials into polyolefins with a design capacity of 2 million tons per year with the corresponding facilities of the OPC is 91.8%. The facility is designed for intermediate storage, packaging and shipment of finished products of polyethylene (high and low density) production plants and polypropylene «ZapSibNeftekhima».
The platform is the end point when sending products to consumers, so the project is linked into a single whole system of receiving, packaging and shipping products. At the same time, the finished product is shipped to the consumer both in bags and in containers. For this purpose, automated dispatch and packaging complexes were provided, which in future will allow the platform's employees to make quick decisions and optimize loading capacities. In the area of responsibility Promstroi works are executed at 90.69%.


September 01, 2018

MOSCOW MAYOR SERGEI SOBYANIN ASSESSED THE PROGRESS OF CONSTRUCTION OF THE "EURO+" MOSCOW REFINERY

Moscow oil refinery Gazprom Neft is completing the construction of a new high-tech combined oil refining unit «Euro+». The construction site at the final stage of the work was inspected by the mayor of Moscow Sergey Sobyanin and Chairman of the Board JSC «Gazprom Neft» Alexander Dyukov. Euro+ is a key project of the second stage of environmental modernization of the Moscow refinery, which Gazprom Neft has been continuing since 2011.
Thanks to the state-of-the-art Euro+ complex, the Moscow refinery will decommission five previous-generation plants and further reduce the company's environmental impact. Advanced technologies will ensure the growth of aviation and automobile fuel production. The largest domestic manufacturers of equipment participate in the construction of the plant.
Moscow mayor Sergei Sobyanin noted that the modernization of the Moscow refinery is a contribution to the ecology of the city. «Currently, the plant is completing the construction of a modern oil refining complex «Euro+», which will replace five obsolete installations of the «small technological ring» of the 60s of the last century. This is the main project of the second stage of modernization of the refinery», - said Sergey Sobyanin.
«Since 2011, Gazprom Neft has invested more than 160 billion rubles in the modernization of the Moscow refinery. Projects were implemented for the transition of the plant to the production of Euro-5 fuel, the construction of innovative biological treatment facilities «Biosphere», the introduction of the industry's first automated environmental monitoring system, a new complex «Euro+» will be built. This is not the end of the modernization program — the work on decommissioning of obsolete «small ring» units and preparation of the construction of the deep oil refining complex is ahead. The aggregate amount of investments of «Gazprom oil» in updating capacities of the enterprise will make 250 billion by 2021», said Chairman of the Board «Gazprom oil» Alexander Dyukov.
To date, the readiness of the complex «Euro+» is 97%. Specialists have already completed the installation of large equipment and basic metal structures. Electrical installation works and setting up of automated systems continue. The launch of the complex is scheduled for 2019.

Text and photo by the press center of JSC «Gazpromneft». Source link.


September 01, 2018

General progress in the construction of the plant for the production of polypropylene capacity of 500 000 tons per year (SCP) exceeded the mark of 90%.
42% of the roads, sites and sidewalks have been completed.
Heat insulation of pipelines is 35% complete.
At 59%, technological pipelines were tested.
80% of the pipelines are delivered through the final inspection.
JSC «Promstroi» started installation of technological pipelines of the flare unit.


August 23, 2018

The project office of OP «Omsk» is actively working in the framework of a large-scale modernization of the Omsk oil refinery. JSC «NIPIGAS», which manages the design, supply and construction works (EPC) of the off-plant facilities (OPC), built in the framework of the second stage of the large-scale modernization program of Omsk refinery «Gazpromneft», in 2018 attracted as one of the construction contractors of the project «Promstroi». The overall progress in the construction of off-site facilities reached 25%. Mounted 14,8 thousand concrete structures, 8.3 thousand. tons of steel structures. Cable installation-11, 5 km, underground pipelines-0.8 thousand tons.

Completion of works in the area of responsibility of JSC «Promstroi» is planned in the third quarter of 2019.


August 14, 2018

Inzhpromstroi, LLC successfully, in the conditions of raising the level of the Zeya river, carries out hydro-washing works on the extraction of inert materials for the needs of the Amur gas processing plant. Zeya is the largest river in the Amur basin. According to the results of work in June, more than 50 000 m3 of materials were washed.


July 23, 2018

On July 23, 1986, the state building trust «Krasnoleninskneftepromstroi» was established in Nyagan city. From this date the historical report of stages of development of «Promstroi» group of companies is being dated. During the large-scale economic crisis of 1990s the trust managed to win the fight over time and preserve its existence despite everything. The tasks of "Krasnoleninskneftepromstroi" were as grand as all that was created during the years of rapid development of oil and gas complex of Western Siberia. Construction of Krasnoleninsky arch is the main purpose of Oil and Gas Industry Construction Ministry, but it is only half of the construction mission in the high north.

The history of our Company is a history of achievements, dozens of constructed industrial petrochemical facilities, production, transportation and oil and gas processing.

Let it be only better!


July 19, 2018

The main value of a successful company is its employees. All employees of our enterprises are absolutely sure in the future, as they work in a stable, socially responsible company that complies with labor legislation with exceptionally "white" payments!

If you have any questions regarding compliance with labor legislation on the part of the employer on the Tobolsk construction site, you can contact the public reception office of "Promstroi" (camp, dormitory 17, room 6). Schedule of work is weekly on Tuesdays from 20-00 to 21-00.

There is also a Hotline of the Tobolsk site of SIBUR, and employees can leave an application for cases of non-payment of salaries by its phone numbers (8-800-301-18-17, 277-717).


July 09, 2018

In the framework of «Construction of Polypropylene production plant of 500 thousand tons annual capacity» of the project «West-Siberian complex of raw hydrocarbons deep conversion into polyolefins which capacity is 2.0 million tons per year, including corresponding off-site facilities» a set of works on adjustment and testing of high-voltage equipment in C57000 transformer substation was carried out and permit for voltage supply was obtained from the North-Ural Department of Rostechnadzor No. Р-199/574.

In advance of 30 calendar days from the schedule of works, we began to conduct a loop test of PPF field equipment.


 

Promstroi Group
of Companies


 

PROMSTROI-GROUP
JSC

Moscow

 
 

Subsidiaries

 

Promstroi
JSC

Nyagan (KMAD)

 

Spetsializirovannoye
Upravlenie No.6
JSC

Stavropol

 

Uralmontazhavtomatika
OJSC

Tyumen

 

KAZMEKHANOMONTAZH
LLP

Republic of Kazakhstan,
Almaty

 

Novopolotsk Metal
Structures Plant
JV LLC

Republic of Belarus,
Novopolotsk

 

Inzhpromstroi
LLC

Blagoveshchensk

 

Associated
undertakings

Talspetsstroi
LLC

Nyagan (KMAD)